CMS-GriPhyN


Project Start Date: Mon 1/7/02
Project Finish Date: Fri 4/11/03

Task_Data

ID
Task_Name
DurationStart_DateFinish_DatePredecessorsResource_Names
1
CS work on Distributed Virtual Data Catalogs
65 daysMon 1/7/02Fri 4/5/02  
2
Develop Replica Catalog
60 daysMon 1/7/02Fri 3/29/02  
3
Investigate concepts of "uploaded" files and algorithms
20 daysMon 1/7/02Fri 2/1/02  
4
Prototype a Grid-wide RC which cataloges files and algorithms
20 daysMon 2/4/02Fri 3/1/023 
5
Investigate Consistency Management Techniques with respect to file existence
20 daysMon 3/4/02Fri 3/29/024 
6
Integrate the VDC/L with the RC
5 daysMon 4/1/02Fri 4/5/025 
7
Integrate VDC with mop_submitter
5 daysMon 1/7/02Fri 1/11/02  
8
Virtualize CMS Distributed Monte Carlo Production
330 daysMon 1/7/02Fri 4/11/03  
9
Integrate CMS Monte Carlo Production Pipeline with the VDC/L
30 daysMon 1/7/02Fri 2/15/02  
10
Investigate "on-the-fly" creation of Objectivity database files and how to catalog them in the VDC
10 daysMon 1/7/02Fri 1/18/02  
11
Integrate VDC directly with DAR (tarball of the CMS software and environment)
5 daysMon 1/7/02Fri 1/11/02  
12
Understand the architecture of DAR
5 daysMon 1/7/02Fri 1/11/02  
13
Produce a VDL file for a DAR pipeline
5 daysMon 1/7/02Fri 1/11/02  
14
Include Pile-up in VDL file for Monte Carlo Production
10 daysMon 1/14/02Fri 1/25/0211 
15
Start a test Monte Carlo Production using the VDC with no validation checks
2 daysMon 1/28/02Tue 1/29/0214,10 
16
Produce 10 000 events using the VDC
0 daysTue 1/29/02Tue 1/29/0215 
17
Validation of Monte Carlo Simulated Data
20 daysMon 1/7/02Fri 2/1/02  
18
Understand how to validate a produced data file
10 daysMon 1/7/02Fri 1/18/02  
19
Determine additional steps in the production pipeline to validate each produced data file
5 daysMon 1/21/02Fri 1/25/0218 
20
Integrate additional validation steps into the production pipeline
5 daysMon 1/28/02Fri 2/1/0219 
21
Start actual Monte Carlo Production using the VDC with automatic validation checks
10 daysMon 2/4/02Fri 2/15/0217 
22
Produce 50 000 events using the VDC
0 daysFri 2/15/02Fri 2/15/0221 
23
Develop VAMPALLA: Virtual dAta iMPALLA
330 daysMon 1/7/02Fri 4/11/03  
24
Develop Test Version of a Virtual Data IMPALA
70 daysMon 1/7/02Fri 4/12/02  
25
Understand the arcitechture of IMPALA
10 daysMon 1/7/02Fri 1/18/02  
26
Understand the architecture of MC_Runjob
10 daysMon 1/7/02Fri 1/18/02  
27
Understand the architecture of BOSS
10 daysMon 1/7/02Fri 1/18/02  
28
Determine in which initial layer the VDC should be integrated
10 daysMon 1/21/02Fri 2/1/0225,26,27 
29
Write interface between the IMPALA integration Layer and the VDC
10 daysMon 2/4/02Fri 2/15/0228 
30
Deploy Test version of VD-IMPALA for Monte Carlo Production
10 daysMon 2/18/02Fri 3/1/0229 
31
Receive Comments
20 daysMon 3/4/02Fri 3/29/0230 
32
Determine a more optimal architecture for a Virtual Data IMPALA
10 daysMon 4/1/02Fri 4/12/0231 
33
Virtual Data IMPALA Version
260 daysMon 4/15/02Fri 4/11/0324 
34
Virtual Data IMPALA Version 1
1 monMon 4/15/02Fri 5/10/0232 
35
Virtual Data IMPALA Version 2
1 monMon 5/13/02Fri 6/7/0234 
36
Virtual Data IMPALA Version 3
1 monMon 6/10/02Fri 7/5/0235 
37
Virtual Data IMPALA Version 4
1 monMon 7/8/02Fri 8/2/0236 
38
Virtual Data IMPALA Version 5
1 monMon 8/5/02Fri 8/30/0237 
39
Virtual Data IMPALA Version 6
1 monMon 9/2/02Fri 9/27/0238 
40
Virtual Data IMPALA Version 7
1 monMon 9/30/02Fri 10/25/0239 
41
Virtual Data IMPALA Version 8
1 monMon 10/28/02Fri 11/22/0240 
42
Virtual Data IMPALA Version 9
1 monMon 11/25/02Fri 12/20/0241 
43
Virtual Data IMPALA Version 10
1 monMon 12/23/02Fri 1/17/0342 
44
Virtual Data IMPALA Version 11
1 monMon 1/20/03Fri 2/14/0343 
45
Virtual Data IMPALA Version 12
1 monMon 2/17/03Fri 3/14/0344 
46
Virtual Data IMPALA Version 13
1 monMon 3/17/03Fri 4/11/0345 
47
Virtualize CMS Remote Data Analysis
1 day?Mon 1/7/02Mon 1/7/02  
48
Integrate Clarens with VDT 1.0
1 day?Mon 1/7/02Mon 1/7/02  
49
Integrate Clarens with VDC/L
1 day?Mon 1/7/02Mon 1/7/02  
50
Remotely analyze 25 000 events using Clarens, the VDC and the VDT
1 day?Mon 1/7/02Mon 1/7/02  
51
Interface Clarens with Root
1 day?Mon 1/7/02Mon 1/7/02  
52
Provide a Clarens data server for Root DB I/O
1 day?Mon 1/7/02Mon 1/7/02  
53
Provide a Clarens data client for the Root Analysis Package
1 day?Mon 1/7/02Mon 1/7/02  
54
US CMS Test Bed
245 days?Mon 1/7/02Fri 12/13/02  
55
Establish initial Test Bed (based on Globus CA)
21 days?Mon 1/7/02Mon 2/4/02  
56
Agree on an Initial Account Management Policy
1 day?Mon 1/7/02Mon 1/7/02  
57
Agree on Software Base
1 day?Mon 1/7/02Mon 1/7/02  
58
Commision Caltech Site
10 daysTue 1/8/02Mon 1/21/0256,57 
59
Identify Machines for US CMS Test Bed
2 daysTue 1/8/02Wed 1/9/02  
60
Provide initial user accounts
10 daysTue 1/8/02Mon 1/21/02  
61
Deploy Software
10 daysTue 1/8/02Mon 1/21/02  
62
Install VDT 1.0
6 daysTue 1/8/02Tue 1/15/02  
63
Condor 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
64
ClassAds 0.9
2 daysTue 1/8/02Wed 1/9/02  
65
DAGMan 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
66
Globus 2.0 beta
2 daysThu 1/10/02Fri 1/11/0263,64,65 
67
GDMP 2.0
2 daysMon 1/14/02Tue 1/15/0266 
68
Install Condor-G 6.3.1
2 daysMon 1/14/02Tue 1/15/0266 
69
Install Objectivity 6.1
5 daysTue 1/8/02Mon 1/14/02  
70
Install initial version of DAR
5 daysTue 1/15/02Mon 1/21/0269 
71
Commision Fermilab Site
10 daysTue 1/8/02Mon 1/21/0256,57 
72
Provide initial user accounts
10 daysTue 1/8/02Mon 1/21/02  
73
Deploy Software
10 daysTue 1/8/02Mon 1/21/02  
74
Deploy VDT 1.0
6 daysTue 1/8/02Tue 1/15/02  
75
Condor 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
76
ClassAds 0.9
2 daysTue 1/8/02Wed 1/9/02  
77
DAGMan 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
78
Globus 2.0 beta
2 daysThu 1/10/02Fri 1/11/0275,76,77 
79
GDMP 2.0
2 daysMon 1/14/02Tue 1/15/0278 
80
Deploy Condor-G 6.3.1
2 daysMon 1/14/02Tue 1/15/0278 
81
Deploy Objectivity 6.1
5 daysTue 1/8/02Mon 1/14/02  
82
Deploy initial version of DAR
5 daysTue 1/15/02Mon 1/21/0281 
83
Commision UCSD Site
10 daysTue 1/8/02Mon 1/21/0256,57 
84
Provide initial user accounts
10 daysTue 1/8/02Mon 1/21/02  
85
Deploy Software
10 daysTue 1/8/02Mon 1/21/02  
86
Deploy VDT 1.0
6 daysTue 1/8/02Tue 1/15/02  
87
Condor 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
88
ClassAds 0.9
2 daysTue 1/8/02Wed 1/9/02  
89
DAGMan 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
90
Globus 2.0 beta
2 daysThu 1/10/02Fri 1/11/0287,88,89 
91
GDMP 2.0
2 daysMon 1/14/02Tue 1/15/0290 
92
Deploy Condor-G 6.3.1
2 daysMon 1/14/02Tue 1/15/0290 
93
Deploy Objectivity 6.1
5 daysTue 1/8/02Mon 1/14/02  
94
Deploy initial version of DAR
5 daysTue 1/15/02Mon 1/21/0293 
95
Commision Florida Site
10 daysTue 1/8/02Mon 1/21/0256,57 
96
Provide initial user accounts
10 daysTue 1/8/02Mon 1/21/02  
97
Deploy Software
10 daysTue 1/8/02Mon 1/21/02  
98
Deploy VDT 1.0
6 daysTue 1/8/02Tue 1/15/02  
99
Condor 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
100
ClassAds 0.9
2 daysTue 1/8/02Wed 1/9/02  
101
DAGMan 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
102
Globus 2.0 beta
2 daysThu 1/10/02Fri 1/11/0299,100,101 
103
GDMP 2.0
2 daysMon 1/14/02Tue 1/15/02102 
104
Deploy Condor-G 6.3.1
2 daysMon 1/14/02Tue 1/15/02102 
105
Deploy Objectivity 6.1
5 daysTue 1/8/02Mon 1/14/02  
106
Deploy initial version of DAR
5 daysTue 1/15/02Mon 1/21/02105 
107
Commision Wisconsin Site
10 daysTue 1/8/02Mon 1/21/0256,57 
108
Provide initial user accounts
10 daysTue 1/8/02Mon 1/21/02  
109
Deploy Software
10 daysTue 1/8/02Mon 1/21/02  
110
Deploy VDT 1.0
6 daysTue 1/8/02Tue 1/15/02  
111
Condor 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
112
ClassAds 0.9
2 daysTue 1/8/02Wed 1/9/02  
113
DAGMan 6.3.1
2 daysTue 1/8/02Wed 1/9/02  
114
Globus 2.0 beta
2 daysThu 1/10/02Fri 1/11/02111,112,113 
115
GDMP 2.0
2 daysMon 1/14/02Tue 1/15/02114 
116
Deploy Condor-G 6.3.1
2 daysMon 1/14/02Tue 1/15/02114 
117
Deploy Objectivity 6.1
5 daysTue 1/8/02Mon 1/14/02  
118
Deploy initial version of DAR
5 daysTue 1/15/02Mon 1/21/02117 
119
Deploy version of the SC2001 MOP demo
10 daysTue 1/22/02Mon 2/4/0258,71,83,95,107 
120
Deploy version of the SC2001 VDC demo
10 daysTue 1/22/02Mon 2/4/0258,71,83,95,107,11 
121
Develop Automatic Procedure for New Account Registration
20 daysTue 2/5/02Mon 3/4/0255 
122
Investigate the use of GRIPE for New Account Registration
10 daysTue 2/5/02Mon 2/18/02  
123
Implement GRIPE for New Account Registration for the US CMS Test Bed
10 daysTue 2/19/02Mon 3/4/02122 
124
Use the Certificate Authority from ESNet
7 days?Fri 2/15/02Mon 2/25/02  
125
ESNet CA comes online
1 day?Fri 2/15/02Fri 2/15/02  
126
Replace the globus-gatekeeper certificate at each site
5 daysMon 2/18/02Fri 2/22/02125 
127
Each user submits a new grid-mapfile entry to each site
1 dayMon 2/25/02Mon 2/25/02126 
128
Test Bed consists of a total of 50 Machines (additional 25)
0 daysFri 2/15/02Fri 2/15/02  
129
Perform a CERN request for Monte Carlo Production using MOP
10 daysTue 2/26/02Mon 3/11/0255,124 
130
Commence regular Monte Carlo Production using IMPALA/MOP
30 daysTue 3/12/02Mon 4/22/02129 
131
Perform a CERN request for Monte Carlo Production using a Virtual Data IMPALA
10 daysMon 4/15/02Fri 4/26/0224 
132
Commence regular Monte Carlo Production using Virtual Data IMPALA
100 daysMon 4/29/02Fri 9/13/02131 
133
Remotely analyze 100 000 events using Clarens
0 daysMon 1/7/02Mon 1/7/02  
134
Test Bed consists of a total of 100 Machines (additional 50)
0 daysFri 6/7/02Fri 6/7/02  
135
Test Bed consists of a total of 200 Machines (additional 100)
0 daysMon 12/9/02Mon 12/9/02  
136
Produced 10 000 000 Monte Carlo Generated Events in one week using a Virtual Data IMPALA
5 daysMon 12/9/02Fri 12/13/02135 
137
Integrate with the US-ATLAS Test Bed
10 days?Mon 1/7/02Fri 1/18/02  
138
Determine any infrastructure requirements and resolve possible conflicts
5 days?Mon 1/7/02Fri 1/11/02  
139
Determine any machine processor requirements
1 day?Mon 1/7/02Mon 1/7/02  
140
Agree to use a common OS, or partition each site into two clusters with two different OS's
1 day?Mon 1/7/02Mon 1/7/02  
141
Determine if AFS is required as a shared file system for ATLAS software
1 day?Mon 1/7/02Mon 1/7/02  
142
Detail any required software
5 daysMon 1/7/02Fri 1/11/02  
143
Agree on an Account Management Policy
5 daysMon 1/7/02Fri 1/11/02  
144
Implement any required compatibile infrastructure
10 daysMon 1/7/02Fri 1/18/02  
145
Create user accounts according to agreed policy
10 daysMon 1/7/02Fri 1/18/02  
146
Integrate with the LIGO Test Bed
1 day?Mon 1/7/02Mon 1/7/02  
147
Integrate with the iVDGL
1 day?Mon 1/7/02Mon 1/7/02  
148
Integrate with the EDG
1 day?Mon 1/7/02Mon 1/7/02  
149 1 day?Mon 1/7/02Mon 1/7/02  
150
CMS MEETING CALENDAR 2002
200 days?Mon 3/4/02Fri 12/6/02  
151
CMS WEEK 1
5 days?Mon 3/4/02Fri 3/8/02  
152
CMS WEEK 2
5 days?Mon 6/10/02Fri 6/14/02  
153
CMS WEEK 3
5 days?Mon 9/23/02Fri 9/27/02  
154
CMS WEEK 4
5 days?Mon 12/2/02Fri 12/6/02  
155
CPT WEEK 1
5 days?Mon 4/15/02Fri 4/19/02  
156
CPT WEEK 2
5 days?Mon 11/4/02Fri 11/8/02