Project Start Date: Mon 1/7/02
Project Finish Date: Fri 4/11/03
| ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|
| 1 | CS work on Distributed Virtual Data Catalogs | 65 days | Mon 1/7/02 | Fri 4/5/02 | ||
| 2 | Develop Replica Catalog | 60 days | Mon 1/7/02 | Fri 3/29/02 | ||
| 3 | Investigate concepts of "uploaded" files and algorithms | 20 days | Mon 1/7/02 | Fri 2/1/02 | ||
| 4 | Prototype a Grid-wide RC which cataloges files and algorithms | 20 days | Mon 2/4/02 | Fri 3/1/02 | 3 | |
| 5 | Investigate Consistency Management Techniques with respect to file existence | 20 days | Mon 3/4/02 | Fri 3/29/02 | 4 | |
| 6 | Integrate the VDC/L with the RC | 5 days | Mon 4/1/02 | Fri 4/5/02 | 5 | |
| 7 | Integrate VDC with mop_submitter | 5 days | Mon 1/7/02 | Fri 1/11/02 | ||
| 8 | Virtualize CMS Distributed Monte Carlo Production | 330 days | Mon 1/7/02 | Fri 4/11/03 | ||
| 9 | Integrate CMS Monte Carlo Production Pipeline with the VDC/L | 30 days | Mon 1/7/02 | Fri 2/15/02 | ||
| 10 | Investigate "on-the-fly" creation of Objectivity database files and how to catalog them in the VDC | 10 days | Mon 1/7/02 | Fri 1/18/02 | ||
| 11 | Integrate VDC directly with DAR (tarball of the CMS software and environment) | 5 days | Mon 1/7/02 | Fri 1/11/02 | ||
| 12 | Understand the architecture of DAR | 5 days | Mon 1/7/02 | Fri 1/11/02 | ||
| 13 | Produce a VDL file for a DAR pipeline | 5 days | Mon 1/7/02 | Fri 1/11/02 | ||
| 14 | Include Pile-up in VDL file for Monte Carlo Production | 10 days | Mon 1/14/02 | Fri 1/25/02 | 11 | |
| 15 | Start a test Monte Carlo Production using the VDC with no validation checks | 2 days | Mon 1/28/02 | Tue 1/29/02 | 14,10 | |
| 16 | Produce 10 000 events using the VDC | 0 days | Tue 1/29/02 | Tue 1/29/02 | 15 | |
| 17 | Validation of Monte Carlo Simulated Data | 20 days | Mon 1/7/02 | Fri 2/1/02 | ||
| 18 | Understand how to validate a produced data file | 10 days | Mon 1/7/02 | Fri 1/18/02 | ||
| 19 | Determine additional steps in the production pipeline to validate each produced data file | 5 days | Mon 1/21/02 | Fri 1/25/02 | 18 | |
| 20 | Integrate additional validation steps into the production pipeline | 5 days | Mon 1/28/02 | Fri 2/1/02 | 19 | |
| 21 | Start actual Monte Carlo Production using the VDC with automatic validation checks | 10 days | Mon 2/4/02 | Fri 2/15/02 | 17 | |
| 22 | Produce 50 000 events using the VDC | 0 days | Fri 2/15/02 | Fri 2/15/02 | 21 | |
| 23 | Develop VAMPALLA: Virtual dAta iMPALLA | 330 days | Mon 1/7/02 | Fri 4/11/03 | ||
| 24 | Develop Test Version of a Virtual Data IMPALA | 70 days | Mon 1/7/02 | Fri 4/12/02 | ||
| 25 | Understand the arcitechture of IMPALA | 10 days | Mon 1/7/02 | Fri 1/18/02 | ||
| 26 | Understand the architecture of MC_Runjob | 10 days | Mon 1/7/02 | Fri 1/18/02 | ||
| 27 | Understand the architecture of BOSS | 10 days | Mon 1/7/02 | Fri 1/18/02 | ||
| 28 | Determine in which initial layer the VDC should be integrated | 10 days | Mon 1/21/02 | Fri 2/1/02 | 25,26,27 | |
| 29 | Write interface between the IMPALA integration Layer and the VDC | 10 days | Mon 2/4/02 | Fri 2/15/02 | 28 | |
| 30 | Deploy Test version of VD-IMPALA for Monte Carlo Production | 10 days | Mon 2/18/02 | Fri 3/1/02 | 29 | |
| 31 | Receive Comments | 20 days | Mon 3/4/02 | Fri 3/29/02 | 30 | |
| 32 | Determine a more optimal architecture for a Virtual Data IMPALA | 10 days | Mon 4/1/02 | Fri 4/12/02 | 31 | |
| 33 | Virtual Data IMPALA Version | 260 days | Mon 4/15/02 | Fri 4/11/03 | 24 | |
| 34 | Virtual Data IMPALA Version 1 | 1 mon | Mon 4/15/02 | Fri 5/10/02 | 32 | |
| 35 | Virtual Data IMPALA Version 2 | 1 mon | Mon 5/13/02 | Fri 6/7/02 | 34 | |
| 36 | Virtual Data IMPALA Version 3 | 1 mon | Mon 6/10/02 | Fri 7/5/02 | 35 | |
| 37 | Virtual Data IMPALA Version 4 | 1 mon | Mon 7/8/02 | Fri 8/2/02 | 36 | |
| 38 | Virtual Data IMPALA Version 5 | 1 mon | Mon 8/5/02 | Fri 8/30/02 | 37 | |
| 39 | Virtual Data IMPALA Version 6 | 1 mon | Mon 9/2/02 | Fri 9/27/02 | 38 | |
| 40 | Virtual Data IMPALA Version 7 | 1 mon | Mon 9/30/02 | Fri 10/25/02 | 39 | |
| 41 | Virtual Data IMPALA Version 8 | 1 mon | Mon 10/28/02 | Fri 11/22/02 | 40 | |
| 42 | Virtual Data IMPALA Version 9 | 1 mon | Mon 11/25/02 | Fri 12/20/02 | 41 | |
| 43 | Virtual Data IMPALA Version 10 | 1 mon | Mon 12/23/02 | Fri 1/17/03 | 42 | |
| 44 | Virtual Data IMPALA Version 11 | 1 mon | Mon 1/20/03 | Fri 2/14/03 | 43 | |
| 45 | Virtual Data IMPALA Version 12 | 1 mon | Mon 2/17/03 | Fri 3/14/03 | 44 | |
| 46 | Virtual Data IMPALA Version 13 | 1 mon | Mon 3/17/03 | Fri 4/11/03 | 45 | |
| 47 | Virtualize CMS Remote Data Analysis | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 48 | Integrate Clarens with VDT 1.0 | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 49 | Integrate Clarens with VDC/L | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 50 | Remotely analyze 25 000 events using Clarens, the VDC and the VDT | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 51 | Interface Clarens with Root | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 52 | Provide a Clarens data server for Root DB I/O | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 53 | Provide a Clarens data client for the Root Analysis Package | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 54 | US CMS Test Bed | 245 days? | Mon 1/7/02 | Fri 12/13/02 | ||
| 55 | Establish initial Test Bed (based on Globus CA) | 21 days? | Mon 1/7/02 | Mon 2/4/02 | ||
| 56 | Agree on an Initial Account Management Policy | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 57 | Agree on Software Base | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 58 | Commision Caltech Site | 10 days | Tue 1/8/02 | Mon 1/21/02 | 56,57 | |
| 59 | Identify Machines for US CMS Test Bed | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 60 | Provide initial user accounts | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 61 | Deploy Software | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 62 | Install VDT 1.0 | 6 days | Tue 1/8/02 | Tue 1/15/02 | ||
| 63 | Condor 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 64 | ClassAds 0.9 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 65 | DAGMan 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 66 | Globus 2.0 beta | 2 days | Thu 1/10/02 | Fri 1/11/02 | 63,64,65 | |
| 67 | GDMP 2.0 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 66 | |
| 68 | Install Condor-G 6.3.1 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 66 | |
| 69 | Install Objectivity 6.1 | 5 days | Tue 1/8/02 | Mon 1/14/02 | ||
| 70 | Install initial version of DAR | 5 days | Tue 1/15/02 | Mon 1/21/02 | 69 | |
| 71 | Commision Fermilab Site | 10 days | Tue 1/8/02 | Mon 1/21/02 | 56,57 | |
| 72 | Provide initial user accounts | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 73 | Deploy Software | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 74 | Deploy VDT 1.0 | 6 days | Tue 1/8/02 | Tue 1/15/02 | ||
| 75 | Condor 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 76 | ClassAds 0.9 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 77 | DAGMan 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 78 | Globus 2.0 beta | 2 days | Thu 1/10/02 | Fri 1/11/02 | 75,76,77 | |
| 79 | GDMP 2.0 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 78 | |
| 80 | Deploy Condor-G 6.3.1 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 78 | |
| 81 | Deploy Objectivity 6.1 | 5 days | Tue 1/8/02 | Mon 1/14/02 | ||
| 82 | Deploy initial version of DAR | 5 days | Tue 1/15/02 | Mon 1/21/02 | 81 | |
| 83 | Commision UCSD Site | 10 days | Tue 1/8/02 | Mon 1/21/02 | 56,57 | |
| 84 | Provide initial user accounts | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 85 | Deploy Software | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 86 | Deploy VDT 1.0 | 6 days | Tue 1/8/02 | Tue 1/15/02 | ||
| 87 | Condor 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 88 | ClassAds 0.9 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 89 | DAGMan 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 90 | Globus 2.0 beta | 2 days | Thu 1/10/02 | Fri 1/11/02 | 87,88,89 | |
| 91 | GDMP 2.0 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 90 | |
| 92 | Deploy Condor-G 6.3.1 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 90 | |
| 93 | Deploy Objectivity 6.1 | 5 days | Tue 1/8/02 | Mon 1/14/02 | ||
| 94 | Deploy initial version of DAR | 5 days | Tue 1/15/02 | Mon 1/21/02 | 93 | |
| 95 | Commision Florida Site | 10 days | Tue 1/8/02 | Mon 1/21/02 | 56,57 | |
| 96 | Provide initial user accounts | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 97 | Deploy Software | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 98 | Deploy VDT 1.0 | 6 days | Tue 1/8/02 | Tue 1/15/02 | ||
| 99 | Condor 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 100 | ClassAds 0.9 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 101 | DAGMan 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 102 | Globus 2.0 beta | 2 days | Thu 1/10/02 | Fri 1/11/02 | 99,100,101 | |
| 103 | GDMP 2.0 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 102 | |
| 104 | Deploy Condor-G 6.3.1 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 102 | |
| 105 | Deploy Objectivity 6.1 | 5 days | Tue 1/8/02 | Mon 1/14/02 | ||
| 106 | Deploy initial version of DAR | 5 days | Tue 1/15/02 | Mon 1/21/02 | 105 | |
| 107 | Commision Wisconsin Site | 10 days | Tue 1/8/02 | Mon 1/21/02 | 56,57 | |
| 108 | Provide initial user accounts | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 109 | Deploy Software | 10 days | Tue 1/8/02 | Mon 1/21/02 | ||
| 110 | Deploy VDT 1.0 | 6 days | Tue 1/8/02 | Tue 1/15/02 | ||
| 111 | Condor 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 112 | ClassAds 0.9 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 113 | DAGMan 6.3.1 | 2 days | Tue 1/8/02 | Wed 1/9/02 | ||
| 114 | Globus 2.0 beta | 2 days | Thu 1/10/02 | Fri 1/11/02 | 111,112,113 | |
| 115 | GDMP 2.0 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 114 | |
| 116 | Deploy Condor-G 6.3.1 | 2 days | Mon 1/14/02 | Tue 1/15/02 | 114 | |
| 117 | Deploy Objectivity 6.1 | 5 days | Tue 1/8/02 | Mon 1/14/02 | ||
| 118 | Deploy initial version of DAR | 5 days | Tue 1/15/02 | Mon 1/21/02 | 117 | |
| 119 | Deploy version of the SC2001 MOP demo | 10 days | Tue 1/22/02 | Mon 2/4/02 | 58,71,83,95,107 | |
| 120 | Deploy version of the SC2001 VDC demo | 10 days | Tue 1/22/02 | Mon 2/4/02 | 58,71,83,95,107,11 | |
| 121 | Develop Automatic Procedure for New Account Registration | 20 days | Tue 2/5/02 | Mon 3/4/02 | 55 | |
| 122 | Investigate the use of GRIPE for New Account Registration | 10 days | Tue 2/5/02 | Mon 2/18/02 | ||
| 123 | Implement GRIPE for New Account Registration for the US CMS Test Bed | 10 days | Tue 2/19/02 | Mon 3/4/02 | 122 | |
| 124 | Use the Certificate Authority from ESNet | 7 days? | Fri 2/15/02 | Mon 2/25/02 | ||
| 125 | ESNet CA comes online | 1 day? | Fri 2/15/02 | Fri 2/15/02 | ||
| 126 | Replace the globus-gatekeeper certificate at each site | 5 days | Mon 2/18/02 | Fri 2/22/02 | 125 | |
| 127 | Each user submits a new grid-mapfile entry to each site | 1 day | Mon 2/25/02 | Mon 2/25/02 | 126 | |
| 128 | Test Bed consists of a total of 50 Machines (additional 25) | 0 days | Fri 2/15/02 | Fri 2/15/02 | ||
| 129 | Perform a CERN request for Monte Carlo Production using MOP | 10 days | Tue 2/26/02 | Mon 3/11/02 | 55,124 | |
| 130 | Commence regular Monte Carlo Production using IMPALA/MOP | 30 days | Tue 3/12/02 | Mon 4/22/02 | 129 | |
| 131 | Perform a CERN request for Monte Carlo Production using a Virtual Data IMPALA | 10 days | Mon 4/15/02 | Fri 4/26/02 | 24 | |
| 132 | Commence regular Monte Carlo Production using Virtual Data IMPALA | 100 days | Mon 4/29/02 | Fri 9/13/02 | 131 | |
| 133 | Remotely analyze 100 000 events using Clarens | 0 days | Mon 1/7/02 | Mon 1/7/02 | ||
| 134 | Test Bed consists of a total of 100 Machines (additional 50) | 0 days | Fri 6/7/02 | Fri 6/7/02 | ||
| 135 | Test Bed consists of a total of 200 Machines (additional 100) | 0 days | Mon 12/9/02 | Mon 12/9/02 | ||
| 136 | Produced 10 000 000 Monte Carlo Generated Events in one week using a Virtual Data IMPALA | 5 days | Mon 12/9/02 | Fri 12/13/02 | 135 | |
| 137 | Integrate with the US-ATLAS Test Bed | 10 days? | Mon 1/7/02 | Fri 1/18/02 | ||
| 138 | Determine any infrastructure requirements and resolve possible conflicts | 5 days? | Mon 1/7/02 | Fri 1/11/02 | ||
| 139 | Determine any machine processor requirements | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 140 | Agree to use a common OS, or partition each site into two clusters with two different OS's | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 141 | Determine if AFS is required as a shared file system for ATLAS software | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 142 | Detail any required software | 5 days | Mon 1/7/02 | Fri 1/11/02 | ||
| 143 | Agree on an Account Management Policy | 5 days | Mon 1/7/02 | Fri 1/11/02 | ||
| 144 | Implement any required compatibile infrastructure | 10 days | Mon 1/7/02 | Fri 1/18/02 | ||
| 145 | Create user accounts according to agreed policy | 10 days | Mon 1/7/02 | Fri 1/18/02 | ||
| 146 | Integrate with the LIGO Test Bed | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 147 | Integrate with the iVDGL | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 148 | Integrate with the EDG | 1 day? | Mon 1/7/02 | Mon 1/7/02 | ||
| 149 | 1 day? | Mon 1/7/02 | Mon 1/7/02 | |||
| 150 | CMS MEETING CALENDAR 2002 | 200 days? | Mon 3/4/02 | Fri 12/6/02 | ||
| 151 | CMS WEEK 1 | 5 days? | Mon 3/4/02 | Fri 3/8/02 | ||
| 152 | CMS WEEK 2 | 5 days? | Mon 6/10/02 | Fri 6/14/02 | ||
| 153 | CMS WEEK 3 | 5 days? | Mon 9/23/02 | Fri 9/27/02 | ||
| 154 | CMS WEEK 4 | 5 days? | Mon 12/2/02 | Fri 12/6/02 | ||
| 155 | CPT WEEK 1 | 5 days? | Mon 4/15/02 | Fri 4/19/02 | ||
| 156 | CPT WEEK 2 | 5 days? | Mon 11/4/02 | Fri 11/8/02 |